Design And Construction Of Automatic Change Over With Generator Trip Off Using Remote

Overview

ABSTRACT

As technological advancement has been on the increase in our society many have fallen in love with technology and world want to have a feel in virtually to everything they do.

An Automatic Changeover Switch switches off the generator and automatically changes over to NEPA. An Automatic Changeover Switch will automatically switch off your generator and change over to MAIN (Public power supply/NEPA) on resumption.

A design has been made in combination of electrical and electronics to change over from one power sources to the other automatically and trip off generator using a remote, and this remote can ON/OFF a generator from a far distance.

TABLE OF CONTENTS

 TITLE PAGE

APPROVAL PAGE

DEDICATION

ACKNOWLEDGEMENT

ABSTRACT

TABLE OF CONTENT

CHAPTER ONE

  • INTRODUCTION
  • BACKGROUND OF THE PROJECT
  • PPROBLEM STATEMENT
  • AIM/OBJECTIVE OF THE PROJECT
  • SIGNIFICANCE OF THE PROJECT
  • PROBLEM OF THE PROJECT
  • SCOPE AND LIMITATION OF THE PROJECT
  • APPLICATION OF THE PROJECT
  • DEFINITION OF TERMS
  • METHODOLOGY
  • PROJECT ORGANISATION

CHAPTER TWO

LITERATURE REVIEW

2.0     LITERATURE REVIEW

2.1     REVIEW OF THE STUDY

2.2     THE SYSTEM COMPONENT ANALYSIS

2.3     OVERVIEW OF RELEVANT TECHNOLOGY

2.4     REVIEW OF RELATED WORKS EXISTING SYSTEM

2.5     SUMMARY OF REVIEWED WORKS

CHAPTER THREE

3.0       CONSTRUCTION METHODOLOGY
3.1       SYSTEM DESIGN

3.2     DESCRIPTION OF THE SYSTEM BUILDING BLOCKS

3.3     CIRCUIT DIAGRAM

3.4     SYSTEM SPECIFICATION AND BLOCK DIAGRAM

3.5     SYSTEM  REMOTE SECTION

CHAPTER FOUR

4.0       RESULT ANALYSIS

4.1     CONSTRUCTION PROCEDURE AND TESTING

4.2     ASSEMBLING OF SECTIONS

4.3     CONSRUCTION OF THE CASING

4.4     TESTING

4.5     EXPECTED AND ACTUAL TEST RESULTS

4.6     PACKAGING OF THE SYSTEM

CHAPTER FIVE

  • CONCLUSIONS
  • RECOMMENDATION

5.3     REFERENCES

CHAPTER ONE

1.0                                       INTRODUCTION

1.1                          BACKGROUND OF THE STUDY

This project is on the design and co of automatic change over and how it can be used to change from one power sources to the other automatically. The design comprises some arrangement that senses the power failure form either of the power sources and drives the electro mechanical switching device (relay) that is capable of changing two poles (live and neutral) to give out light or be on standby to generator side.

Power instability or outage in general does not promote development in the public and private sector. The investors do not feel secure to come into a country with constant or frequent power failure. These limit the development of industries. In addition, there are processes that cannot be interrupted because of their importance for instance, surgery operation in hospitals, transfer of money between banks and lots more. Power instability and outage in developing countries (Nigeria) creates a need for alternative sources of power to backup the mains supply.

Automatic changeover switches find a wide application scope wherever the reliability of electrical supply from the utilities is low and it is used in lighting/motor circuits wherever continuity of supply is necessary, for switching to an alternative source from main supply and vice versa.

Electronic components such as relay transformer diodes were used thereby making the project less expensive for the implementation of the project and commercial application.

Moreover, the cost suitability and availability of the required components for the project circuitry were some of the major factors considered by the designer.

1.2                                   PROBLEM STATEMENT

Power failure or outage in a country, state or city is highly detrimental to development in public and private industries. The insecurity associated with constant or frequent power failure or outage brings about limitation to power consistent investments, thus hampering the development of industries and multinational ventures. Processes like carrying out surgical operations in hospitals, laboratories which require constant power supply for research, money transactions between banks and more require constant use of uninterrupted power. In other to solve this problem, an automatic changeover switch was invented. This research covers the design and construction of a single phase automatic power changeover. It has the capacity to automatically switch power from  national grid to generator and vice versa, once there is power failure in any of the two power supplies and at the same time has the capacity of shutting down a generator set once the mains grid is been restored.

1.3                                      AIM/OBJECTIVES

To design a circuit that will automatically change over from main power supply (PHC) to power generating set and vice versa, and using a remote control to ON/OFF the generator set with the help of electro mechanically switching device that is being controlled by electronics component

1.4                          SIGNIFICANCE OF THE PROJECT

The automatic change over switch, the switch aimed at achieving the following automatic actions;

  • To change power over to generator
  • To change back to PHC
  • To change the generator.

The automatic change over unit can be operated in single or three phase system. The automatic change over switch has the following advantages;

  • It minimizes damages to lives/equipment since it has its own monitoring system and its switching requires no human contact with the switch, thus eliminating human error.
  • It reduces its change over timing to the minimum due to its fast response to power outage.
  • It maintains high quality of service through its fast and prompt response.
  • Moreover, the size and captivity of the unit will depend upon the load for which it will be used. The unit is also portable, easy, convenient and safe to install.
  • Genset is put off automatically when main power resumes.
  • Minimized physical activity is to start the generator.
  • It can operate in low voltage.
  • Fuel is saved due to auto stop facility.

1.5                           PROBLEMS OF THE PROJECT

In every home, office or industries, automatic power changeover  plays a vital role, that is, It provides a means of switching from utility AC mains to generator in the case of power failure; This project has been improved on the existing types of electromechanical device that has being in use over the years.

In the course of designing this project, different kinds of problem was notice such as:

  • Difficulty in troubleshooting with circuit without the circuit diagram
  • Difficulty in connecting the output without short-circuiting, until a multiplexing circuit was gotten.
  • Difficult in wiring because of the strong wiring the project required.

1.6                SCOPE AND LIMITATION OF THE STUDY

This work covers only a one phase automatic changeover which can only be used for providing a means of switching from one phase of AC mains to another in the case of failure in public utility. It is limited to

  •  Phase – one phase
  • Capacity – single Phase
  • Input Volt – 220v

1.7                                      APPLICATIONS OF THE PROJECT

  1. This circuit can be used as a home lighting system with few modifications.
  2. It can be used to drive other DC loads like a DC motor of any electronic appliance or other toy applications.
  3. home,
  4. office,
  5. worship places
  6. workshops or industries, etc

1.8                                            DEFINITION OF TERMS

CHANGEOVER: Generally, a changeover switch is a system which could be operated manually or automatically , that changes one source of power supply to another source in case of power failure from either of the two sources.

RELAY: relay is one of the major components used in this work which is an electrical device, typically incorporating an electromagnet, which is activated by a current or signal in one circuit to open or close another circuit.

POWER FLUCTUATIONS: is a periodic dip or spikes in the electrical current of any given circuit.

POWER FAILURE: is a short- or long-term loss of the electric power to an area.    

1.9                                         METHODOLOGY

To achieve the aim and objectives of this work, the following are the steps involved:

  1. Study of the previous work on the project so as to improve it efficiency.
  2. Draw a block diagram.
  • Test for continuity of components and devices,
  1. Design and calculation for the changeover was carried out.
  2. Studying of various component used in circuit.
  3. Construct a digital changeover circuit.
  • Finally, the whole device was cased and final test was carried out.

1.10                        PROJECT WORK ORGANIZATION

The various stages involved in the development of this project have been properly put into five chapters to enhance comprehensive and concise reading. In this project thesis, the project is organized sequentially as follows:

Chapter one of this works is on the introduction to changeover switch. In this chapter, the background, significance, objective limitation and problem of changeover switch were discussed.

Chapter two is on literature review of changeover switch. In this chapter, all the literature pertaining to this work was reviewed.

Chapter three is on design methodology. In this chapter all the method involved during the design and construction were discussed.

Chapter four is on testing analysis. All testing that result accurate functionality was analyzed.

Chapter five is on conclusion, recommendation and references.

Chapter Two: Literature Review

2.0 INTRODUCTION:

This chapter provides the background and context of the research problems, reviews the existing literature on the design and construction of automatic change over with generator trip off using remote, and acknowledges the contributions of scholars who have previously conducted similar research [rev65731] …

Document Information

    • Format: DOC/PDF
    • Title: Design And Construction Of Automatic Change Over With Generator Trip Off Using Remote:

YOU MAY LOVE THESE (Recommended)

  • Impact Of Cognitive Conflict Instructional Model On Conceptual Change And Performance In Genetics Among Secondary School Biology Students

    118 Pages 1 - 5 Chapters 29,115 Words DOC/PDF Format Instant Download UPN95195

  • How to write the “Impact Of Change Management In Banking Industry” Project

    To start a project on impact of change management in banking industry, follow these guidelines: The research topic of this study is the impact of change management in nigerian banking industry, a study of united bank for africa (uba) station road, enugu. The research was a descriptive research, the researcher made use of primary sources and secondary sources of data. The primary sources of …

    79 Pages 1 - 5 Chapters 1,698 Words DOC/PDF Format Instant Download UPN62286

  • Techniques for writing the “GSM Based Remote Switching System” Project

    Introduction 1. 1 background of study has technology transformed humankind into omniscient being? Years back, communication was done through difficult means like travelling to the destination of the second party, posting letters est. Today people can communicate easily through various means like e-mailing, face booking, gsm etc. The new age of technology has redefined communication, most people nowadays have access to mobile phones and […]

    62 Pages 1 - 5 Chapters 6,787 Words DOC/PDF Format Instant Download UPN63956

  • Techniques for writing the “Free Electricity Generator Using DC Motor” Project

    To develop a project on free electricity generator using dc motor, follow these approaches: The study for the search of renewable sources of energy is now a major concern worldwide as replacement to the high demand of fossil fuels. Majority of the electricity that is generated uses the faraday’s law, the electromagnetic induction. This law led to new technologies that even brought up th…

    35 Pages 1 - 5 Chapters 7,198 Words DOC/PDF Format Instant Download UPN66339

  • Writing strategies for the “Design And Construction Of IR Remote Controlled Light” Project

    To undertake a project on design and construction of ir remote controlled light, follow these effective ways: This project work deals on the design and construction of an ir based remote control for an electronic/electrical device say electric lamp with the aim of switching on/off of the lamp at discretion and from a distance. It also eliminates the inconveniences associated with manual switching of bed …

    47 Pages 1 - 5 Chapters 7,059 Words DOC/PDF Format Instant Download UPN64833

  • Steps for writing the “Design And Construction Of Automatic Smart Waste Bin” Project

    To write a project on design and construction of automatic smart waste bin, follow these structure: The main objective of the project is to design a smart dustbin which will help in keeping our environment clean and also eco friendly. Nowadays technologies are getting smarter day-by-day so, as to clean the environment we are designing a smart dustbin by using arduino. This smart dustbin managem…

    45 Pages 1 - 5 Chapters 6,761 Words DOC/PDF Format Instant Download UPN85748

  • Guide for writing the “Design And Construction Of Automatic Phase Selector” Project

    Introduction as the growing population of human race widens the gulf between energy supply and energy demand, the imbalance in energy availability sent researchers into excavating for a way of settling this age long squabble. A lasting solution is vested on alternative use of the renewable energy source, a project that is yet to be widely applied. Hence, the continuation of the unsettled yearns for sufficient power. Consequently, the p […]

    51 Pages 1 - 5 Chapters 5,437 Words DOC/PDF Format Instant Download UPN63942

  • To carry out a project on design and construction of automatic fence light controller, follow these effective methods: The very fundamental reasons behind this project assignment is to expose student to the very important aspect of private and independent research work not only theories but also subsequent translation of the theoretical research work into a particular function system. The project construction of …

    25 Pages 1 - 5 Chapters 2,587 Words DOC/PDF Format Instant Download UPN63990

  • To start a project on design and construction of automatic change-over for three phases, follow these guidelines: The main aim of any electric power supply in the world is to provide uninterrupted power supply at all times to all its consumers. Although in developing countries, the electric power generated to meet the demands of the growing consumers of electricity is insufficient hence instability and outag…

    50 Pages 1 - 5 Chapters 6,521 Words DOC/PDF Format Instant Download UPN64102

  • To develop a project on design and construction of an automatic water pump controller with water timed flushing mechanism, follow these approaches: This project presents the concept of a control system into an automatic water pump controller. One of the motivations for this project is the need to bring a solution to the problem of water shortage in various places eliminating the major culprit, waste of water during pumping, dispensing into o…

    65 Pages 1 - 5 Chapters 7,929 Words DOC/PDF Format Instant Download UPN66459

Live Chat