Design And Installation Of Single Phase Domestic Power System

Overview

ABSTRACT

The main objective of the project is to design and install the building electrical services for a one bedroom duplex. Due to the location, the most reliable source of electrical power is the mains national grid power. In order to achieve the main objective and to specify the size and number of back-up generators to be employed, the final circuits consisting of lighting and power sockets is designed first. The lighting design is done using the lumen method which takes into consideration the size and use of the room being lit. Power points layout design is done by considering the needs of the final user of the premises in every room; this ensures that the need for electrical power is  fulfilled in the design. This is located at a convenient area and caged within the site compound. To ensure coordinated operation of the Miniature Circuit Breakers (MCB) when safeguarding against the effects of overloads and short circuits, discrimination between the devices is observed. This has enabled the system to switch off only the breaker closest to the fault without disruption of supply to other areas.

TABLE OF CONTENTS

COVER PAGE

TITLE PAGE

APPROVAL PAGE

DEDICATION

ACKNOWELDGEMENT

ABSTRACT

CHAPTER ONE

1.0      INTRODUCTION

1.1      BACKGROUND OF THE PROJECT

  • AIM OF THE PROJECT
  • OBJECTIVE OF THE PROJECT
  • SCOPE OF THE PROJECT
  • SIGNIFICANCE OF THE PROJECT

CHAPTER TWO

LITERATURE REVIEW

  • OVERVIEW OF ELECTRICAL DESIGN
  • OVERVIEW OF ELECTRICITY
  • HISTORICAL BACKGROUND OF ELECTRICITY
  • DEFINING PARTS OF THE ELECTRICAL PLAN
  • DETERMINING APPLICABLE DESIGN PLAN STANDARDS
  • CODES AND STANDARDS
  • END – USER ACCESSORIES

CHAPTER THREE

3.0     METHODOLOGY

3.1      LIGHTING DESIGN

3.2      BEDROOM DUPLEX LIGHTING DESIGN

3.3     ELECTRICAL POWER CIRCUITS

3.4      ELECTRICAL SERVICE NETWORK

3.5      POWER CIRCUIT DESIGN

3.6      PROTECTION SYSTEMS

3.7      PROTECTION SYSTEM EQUIPMENT

3.8      DISCRIMINATION AND PROTECTION SYSTEM CO-ORDINATION

3.9      LIGHTNING PROTECTION

CHAPTER FOUR

4.0      DESIGN ANALYSIS AND DISCUSSION

4.1     SAMPLE LUMEN METHOD OF LIGHTING DESIGN CALCULATION FOR THE DUPLEX

CHAPTER FIVE

  • CONCLUSIONS
  • RECOMMENDATION AND FUTURE WORK
  • REFERENCES

CHAPTER ONE

1.0                                                            INTRODUCTION

1.1                                               BACKGROUND OF THE STUDY

For all building construction or remodeling building projects, the owner or occupant must first have a concept for the new design, and then the architect or designer can produce a set of building plans. These plans convey all the required information to the local inspection authority and associated building trades so that the construction or remodeling can take place. Because commercial and industrial buildings contain a number of electrical systems, these plans include specific electrical designs and additional documentation to verify that the design conforms to all required building codes.

An electrical design goes through several important stages of development. First, the designer must understand the scope of the project. Then, the designer defines and designs each component (such as general office areas, specialized machinery, and power distribution equipment) to recognized industry standards. Finally, these individual components are compiled to form the final presentation for the design.

The main objective of the project is to do a building electrical services design for a one bedroom duplex. In order to achieve the main objective, the project work is split into other smaller but related sections and scopes with specific targets to be met. The areas of utmost interest and covered exhaustively and in detail in this project are thus:

  • Lighting design
  • Power points layout design
  • Cables sizing
  • Power back-up system
  • Protection system design
  • Discrimination and co-ordination system
  • Power factor correction

1.2                                                   OBJECTIVE OF THE STUDY

The main aim of the project is to do a building electrical services design for a one bedroom duplex which is carried out by the student. At the end of this work, the student shall be able to:

  • Identify the steps in the electrical design
  • Determine the scope of an electrical design
  • Interpret the various components of an electrical plan, including general and specialized loads, lighting systems, and distribution
  • Recognize the symbols used in electrical plan
  • Identify the standards and regulations that guide the electrical design

1.3                                                       SCOPE OF THE STUDY

Engineering specialization consists of various fields. One of these fields is the building design and construction which has six different categories: civil, structural, mechanical, electrical, environmental and materials engineering.

This project will focus on the electrical category of building design and construction from the electrical services design engineer’s perspective rather than that of the installation electrician or architect. The main focus is to ensure that the electrical system meets the following criteria:

  • Reliability
  • Durability
  • Maintainability
  • Efficiency
  • Economy

1.4                                               SIGNIFICANCE OF THE STUDY

The need to have a standard an electrical service design is not only profit to the owner or occupant of the building but also helpful to the designer of the building. For the occupant or the owner of the house, it give them safety, while for the designer it makes room for more contract.

Every electrical design has unique requirements, depending on the scope of the project. The project scope is determined by the customers’ requirements and the type of structure that the customer will occupy. For example, if the project requires new electrical systems for an existing building, then the electrical designer works to incorporate all the new electrical wiring into the existing system. The designer must evaluate the existing electrical system to ensure that existing electrical systems can accommodate new additional electrical loads that will be imposed on them. When the design is for a new pro- posed facility, then the scope of the project is much greater. Electrical designs for these types of projects require an entirely new electrical system design.

CHAPTER FIVE

5.1                                                                 CONCLUSIONS

In this project, an attempt has been made to come up with an appropriate lighting scheme and distribution system layout for a proposed duplex. Various sizing of cables have also been discussed to supplying power to the entire duplex building. Overload, short-circuit and lightning protections have also been included in the building electrical services design.

These achievements are all in line with the main objectives of the project. Therefore, the laid down objectives at the start of the project were successfully met during the entire project process.

Some challenges arose during the project process and appropriate solutions were considered. A challenge such as load balancing for the duplex was not an easy and smooth task. However, a solution was found by first assigning each of the overall loads of the duplex to a single independent supply phase.

As a result of appropriate solutions to the challenges faced and achievement of the project main objectives, the building electrical services design for a 3 bedroom duplex project was indeed a success

5.2                                         RECOMMENDATION FOR FUTURE WORK

Small computer programs and macros can be written and coded to be able to compute the load calculations, currents drawn by various load circuits and voltage drops across the cable conductors. The programs can further be developed to be able to pick appropriate cables from the IEE tables for cable and conductors databases depending on the calculation results. Hence it will do cable sizing for all the building electrical power systems. Further development of the computer programs to display and give all the building electrical services power systems parameters at strategic points is also necessary and recommended. These programs when integrated leads to development of a comprehensive software for the building electrical services. This will save the manual time and energy in this demanding project work due to its wider scope. This will also enable computational implementation of the project in future

Chapter Two: Literature Review

2.0 INTRODUCTION:

This chapter provides the background and context of the research problems, reviews the existing literature on the Design And Installation Of Single Phase Domestic Power System, and acknowledges the contributions of scholars who have previously conducted similar research [REV66134] …

Document Information

    • Format: DOC/PDF
    • Title: Design And Installation Of Single Phase Domestic Power System:

YOU MAY LOVE THESE (Recommended)

  • To start a project on Use Of Manpower Audit For Efficient Man Power Planning, follow these guidelines: The purpose of this research is to investigate on the use of manpower audit for efficient manpower planning in Enugu State Broadcasting Service. In carrying out the research, the researcher used such instrument as questionnaires, interviews and published work to obtain all the relevant data requi…

    89 Pages 1 - 5 Chapters 10,155 Words DOC/PDF Format Instant Download UPN62714

  • Techniques for writing the “Study Of Impact Of Frequency Deviation On Power System” Project

    To develop a project on Study Of Impact Of Frequency Deviation On Power System, follow these approaches: The operation and the development of power system networks introduce new types of stability problems.  The effect of the power generation and consumption on the frequency of the power system can be described as a demand/generation imbalance resulting from a sudden increase/decrease in the demand …

    62 Pages 1 - 5 Chapters 11,700 Words DOC/PDF Format Instant Download UPN65119

  • INTRODUCTION Before a designer can relate his requirements dearly in a construction industry, a drawing is to be prepared; this is because the drawing serves as a general means of communication. Thus, the drawing is adopted mostly, then other means of communication in engineering sectors. A structured engineer mostly engages himself in designs on construction of structures. Like roads, bridges, railways, dams, buildings and other publi […]

    28 Pages 1 - 5 Chapters 3,114 Words DOC/PDF Format Instant Download UPN62990

  • To undertake a project on Single Line To Ground Fault Analysis In 11kV Distribution Feeder, follow these effective ways: The aim of this research work is to carry out fault analysis of 11KV distribution power system. Electric power is an essential facilitator for sustainable development of the modern nation state. While Nigeria is reported to suffer from severe shortages of electric power the condition of some of i…

    41 Pages 1 - 5 Chapters 7,092 Words DOC/PDF Format Instant Download UPN66282

  • To write a project on Role Of Marketing Research In Enhancing Customer Service Level In The Power Industry, follow these structure: Marketing research in now giving position in the solving or organisation problems, both private and public owned organisations. The importance of marketing reach to organisation cannot be over emphasised. Organisation as an open system cannot operate in isolation, they must react to environment (…

    42 Pages 1 - 5 Chapters 4,755 Words DOC/PDF Format Instant Download UPN64279

  • To carry out a project on Psychosocial Effect Of Single Parenthood On Adolescent Self Concept, follow these effective methods: Although recent evidence implies linkages among depression or depressive symptoms, self-esteem, history of childhood abuse, and parenting. Children living in single family homes have different outlooks on life than children raised in a home with two parents. The financial stability, psychological…

    62 Pages 1 - 5 Chapters 10,338 Words DOC/PDF Format Instant Download UPN80709

  • How to write the “Production Of Domestic Powder” Project

    To start a project on Production Of Domestic Powder, follow these guidelines: This research project is aimed at producing domestic powder and consequently, three different types of powder were produced, namely, simple face powder (pan-cake), medicated/Antiseptic powder (dristing powder). During the various production Talcum, Zinc-oxide, Perfume, Menthol, Tragasan 300 DP (T…

    72 Pages 1 - 8 Chapters 8,771 Words DOC/PDF Format Instant Download UPN62895

  • Techniques for writing the “Problems Of Manpower Development In Government Parastatals” Project

    To develop a project on Problems Of Manpower Development In Government Parastatals, follow these approaches: The focus of this research work is on the problem of manpower development in government parastatals with special reference to Enugu State Marketing Company which is the case study. The researchers presents the introductory part of the write-up which dealt with the historical background of Enugu S…

    76 Pages 1 - 5 Chapters 9,260 Words DOC/PDF Format Instant Download UPN62197

  • To undertake a project on Power Supply And The Performance Of Small And Medium Scale Industries, follow these effective ways: This research work centers on the power supply and the performance of small and medium scale industries in Nigeria from 1986 – 2010. carrying out this study, secondary data were collected and empirical analysis was made to achieve these objectives, multiple regression were used in anglicizing the…

    66 Pages 1 - 5 Chapters 6,988 Words DOC/PDF Format Instant Download UPN63880

  • Steps for writing the “Power Amplifier” Project

    INTRODUCTION Power amplifier is an electronic device, which is used to increase sound energy. In other words, the final stage which must driven a given load e.g mechanical indicator, a loudspeaker cathode roy tade, magnetic deflection coil, a transmitting accrual of a communication network. Power amplifier is also used in regulation power supplies, chopper amplifier, motor controller etc. In general the load will by its nature, demand […]

    38 Pages 1 - 5 Chapters 3,996 Words DOC/PDF Format Instant Download UPN63998

Live Chat